OBJECT:
The project constructed is mainly hydraulic and involved the construction of:
- The sewer pipes (collectors and main) of the internal network of the settlement of Agia Paraskevi of approximately 6,140.00 m.
- Of the sewage transport pipeline to the point of confluence with the Vassilikos Wastewater Treatment Plant, approximately 1,660.00m long.
- The construction of a pumping station in the north-western part of the settlement, in order to connect the residential areas located west and south-west of the existing settlement and a push pipeline of approximately 320.00m to the sewage network