5. FROMGOOD FRIDAY MEETING:

PROJECT TITLE: CONSTRUCTION OF AN INTERNAL NETWORK OF HOLY FRIDAY WASTE AND CONNECTOR WITH COLLECTOR - THERMIS

INITIAL BUDGET: 2,210,846.88 EUROS (INCLUDING VAT)

OBJECT:

The project constructed is mainly hydraulic and involved the construction of:

The company successfully constructed the construction of the sewage pipelines (collectors and main) of the internal network of the settlement and the sewage transport pipeline up to the consulting position at the Vasilikon Wastewater Treatment Plant, with the final recipient being the new sewage treatment facility of the Municipality of Thermi. In addition, the construction of a pumping station in the North-Eastern part of the settlement is planned, in order to connect a small part of the pre-existing settlement and the expansion area of the city plan to the east with the sewage network.